1. Give a detailed description on “Detailed Project Report”. Indicate the Pros and Cons of it also.

2. What is Project Management Information System? Why is a Project Management Information System considered to be of immense importance in a project? In designing a Project Management Information System what parameters are to be spelt out clearly in line with the objectives of the Project management Information System?

3. Technology and processes play crucial role in certain projects. What the key issues are in regards to choice of technology, equipment and processes at the stage of formulation of Detailed Project Report?

4. Given the activity mean and Standard Deviation, Find the probability that the project will take more than 10 weeks to complete.

Activity Mean Standard Deviation
1 – 2 5 1
2 – 3 4 1
1 – 3 8 1

5. For the following network data,

(a) Identify the Critical Path and its duration

(b) Calculate the total network slack time.

Job

(Activity)

Network

Initial Node

Network

Final Node

Estimated Time (days)

 

A 1 2 2
B 1 3 3
C 1 4 3
D 2 5 3
E 2 9 3
F 3 5 1
G 3 6 2
H 3 7 3
I 4 7 5
J 4 8 3
K 5 6 3
L 6 9 4
M 7 9 4
N 8 9 3
O 9 10 2

 